Valuable consideration
Other than contracts made under seal, and subject to the Contracts (Rights of Third Parties) Act, the courts will not enforce gratuitous promises. There must be valuable consideration.
Valuable consideration is 'something of value in the eye of the law' (Thomas v Thomas). Clearly, the payment of money or a promise to pay money is valuable consideration. However, 'in the eyes of the law' other acts, however insignificant, may provide valuable consideration.
For example, a promise to give £50 'if you will come to my house' was held to be valuable consideration in Gilbert v Ruddeard. However, as a general rule, a moral obligation does not provide valuable consideration; for example, a promise made 'in consideration of natural love and affection' (Brett v J.S.). Nor is a pre-existing legal obligation sufficient to provide valuable consideration, often referred to as 'past consideration'.
The giving of a collateral warranty by an architect in consideration of terms of appointment that have already been fulfilled or the giving of a guarantee by a construction company in consideration of a payment under the construction contract, are examples of past consideration.
Valuable consideration need not be adequate consideration in a sense that the courts are not concerned as to the fairness of the bargain between two contracting parties. For this reason payment of nominal consideration is sufficient. Collateral warranty agreements usually provide that consideration for the agreement shall be the payment by the promisee to the promisor of the sum of £1 or £10. Whether it be £1 or £10, this consideration, though nominal, is valuable consideration for the purposes of enforcing the warranty.
Valuable consideration must support the promise and not the contract. That is to say there must be some detriment to the promisee (the giving of value) or some benefit to the promisor (receipt of value).
In many cases, a detriment to the promisee will be the same as a benefit to the promisor, for example, a sub-contractor promises to carry out piling works in consideration for which the main contractor promises to pay the price of those works. The carrying out of the piling works and the promise to pay the price of the works are respectively both detriments and benefits. However, whilst consideration must move from the promisee it is not necessary for consideration to move to the promisor.
For example, if A promises to B that A will guarantee the repayment of a loan of finance to be made by B to C, whilst A derives no benefit from the transaction if B, in consideration of A's promise, makes the loan to C, then B will suffer a detriment which provides valuable consideration moving from B (the promisee) to A (the promisor) in respect of a contract of guarantee.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.